The effect of the order will be that during the dates and times specified below all vehicles will be prohibited from proceeding along the length of road known as Oakham Road from the junction with Lyndon Road to Uppingham Road
The closure is to enable Network Rail to undertake bridge demolition and rebuilding works.
The duration of the Closure shall be for a maximum period of six months from 12th April 2021 or until the works are completed.
It is anticipated the works will take 85 days. The closure shall come into force when the appropriate signs and diversion route are erected on site.
The duration of the Closure shall be as follows: from 12th April 2021 to 5th July 2021
The alternative route during the closure will be via the route shown on the attached plan
TEMPORARY ROAD CLOSURE Oakham Road,Manton CP